Government Resolution, dated 30 September 2026, is issued under Section 79A of the Maharashtra Co-operative Societies Act, 1960

About this GR: This Government Resolution, dated 30 September 2026, is issued under Section 79A of the Maharashtra Co-operative Societies Act, 1960, and supersedes the earlier redevelopment GR dated 4 July 2019. It sets out the complete procedure a Co-operative Housing Society must follow — from appointing a PMC to signing a registered Development Agreement.

FAQ'S : 

Critical & Very Important — Rules That Can Make or Break the Process

1. What is this new GR and when was it issued?

This is a Government Resolution (GR) No. सगृयो-2026/प्र.क्र.108/14-स, issued by the Cooperation, Marketing and Textiles Department, Government of Maharashtra, on 30 September 2026. It lays down the complete, step-by-step procedure that a Co-operative Housing Society must follow for redevelopment of its building.

2. Which earlier GR does this one replace?

This GR dated 30 September 2026 supersedes the earlier redevelopment GR dated 4 July 2019. Societies, committees and PMCs should now follow only the 2026 GR for any redevelopment decision, and should treat the 2019 GR's redevelopment procedure as no longer applicable.

3. Under which law is this GR issued?

The GR is issued under Section 79A of the Maharashtra Co-operative Societies Act, 1960. This section allows the State Government to issue binding directions to co-operative societies, which means this GR's procedure is not optional guidance but a mandatory requirement.

4. Does this GR apply to all types of redevelopment?

Yes. The GR applies to builder-led redevelopment, self-redevelopment, and redevelopment carried out by a federation or cluster of societies. Whatever model a society chooses, the core steps in this GR — appointing a PMC, holding proper SGMs, inviting tenders and signing a registered agreement — must be followed.

5. Can a Registrar-appointed administrator decide on redevelopment?

No. The GR is clear that only a properly elected Managing Committee of the society can take decisions on redevelopment. An administrator appointed by the Registrar in place of an elected committee does not have this power, and any redevelopment decision taken by an administrator alone would be improper.

6. Who has the power to initiate redevelopment in a society?

The elected Managing Committee, acting with the approval of the General Body in a properly convened Special General Body Meeting (SGM), has this power. No individual office-bearer, and no committee acting alone without General Body approval, can validly start the redevelopment process on their own.

7. How many PMC/architect quotations must a society obtain, and from where?

A society must obtain a minimum of three quotations for appointing a PMC or architect. These quotations must come from professionals empanelled with the government or with the relevant local authority, so a society cannot appoint just any outside professional of its own choosing without checking this panel.

8. What is the minimum physical-presence rule for the SGM that decides redevelopment matters?

At least 51% of the society's total members must be physically present at the meeting for its decisions to be valid. Members joining only by video conferencing can add to the quorum and majority count beyond this 51%, but they cannot be counted as a substitute for the required 51% physical presence itself.

9. Can video conferencing fully replace physical attendance in these meetings?

No, not for the compulsory 51% physical presence requirement. Video conferencing is allowed and encouraged for members who cannot attend in person, but only to help reach the overall quorum and majority numbers once the mandatory 51% physical presence is already satisfied.

10. How many tenders must a society receive before proceeding?

A society must receive a minimum of three valid tenders before it can proceed to developer selection. This requirement is meant to ensure genuine competition and the best possible terms for the society, rather than a single developer being selected without comparison.

11. What happens if fewer than 3 tenders are received?

The GR requires a minimum of three tenders. If fewer are received, the tender period is extended by 15 days first, and then by a further 7 days if still short. The tenders actually received are then placed before the SGM.

12. Who can preside over the SGM that selects the developer?

An Authorised Officer appointed by the Registrar must attend the developer-selection SGM, verify attendance and quorum, and supervise the voting. The meeting must be held in the presence of the Registrar's representative.

13. How is the developer finally selected?

The developer is selected by a resolution passed by a majority of members at the SGM, normally by show of hands. If at least one-fifth of the society's total members demand it in writing, the vote must be by secret ballot. The appointment also requires written consent from at least 51% of the society's total members.

14. Is video recording of the developer-selection meeting compulsory?

Yes, video recording of this meeting is compulsory. The Secretary must retain a copy of the recording, and a copy must also be filed with the Registrar, so there is a verifiable record of how the decision was reached.

15. Can a committee member or office-bearer become the developer?

No. A committee member or office-bearer of the society cannot be the developer, and cannot be a relative of the developer. This prevents conflicts of interest in the selection process.

16. Must the Development Agreement be registered?

Yes. The Development Agreement between the society and the developer must be registered under the Registration Act, 1908. An unregistered agreement does not give the society the legal protection this GR intends.

17. Must each member's PAAA also be registered?

Yes. Each member's individual Permanent Alternative Accommodation Agreement (PAAA) must also be registered, within three months of the Development Agreement being registered. This gives every individual member, not just the society as a whole, a legally enforceable document for their own flat.

18. What is the maximum time allowed for construction?

The Development Agreement must fix the project completion period, counted from the date of the plinth (foundation) completion certificate. It may not exceed two years, and only in exceptional cases may it extend to three years.

19. When can members vacate their flats?

Members should vacate their existing flats only after all legal approvals for the project are in place and their own individual PAAA has been registered. Vacating before these protections are secured leaves a member without the legal safeguard this GR is designed to provide.

20. What happens if office-bearers violate this GR?

Office-bearers and committee members responsible for a violation can be held liable under Section 79A(3) read with Section 78A of the Maharashtra Co-operative Societies Act, 1960. This means failing to follow this GR's procedure is not just an irregularity — it can lead to personal accountability for those responsible.

Important — Meeting, Tender & Agreement Procedure

21. How is a Special General Body Meeting (SGM) for redevelopment called?

An SGM can be called when at least one-fifth of the society's total members submit a written requisition for it. Once such a requisition is received, the Managing Committee must convene the SGM within two months.

22. What is the notice period for this SGM?

Under the GR, every member must receive the agenda at least 14 days before a redevelopment SGM, with proof of delivery kept in the society's records. For the developer-selection SGM, notice is sent by hand, post or e-mail. A meeting adjourned for lack of quorum needs 7 days' notice.

23. Can members suggest changes before the SGM?

Yes. Members have the right to submit their written suggestions on the redevelopment proposal at least 8 days before the SGM is held. The Managing Committee should consider these suggestions while finalising the agenda and proposal placed before the meeting.

24. What quorum is required for this SGM?

Quorum is two-thirds of the society's total members. If it is not met, the meeting is adjourned and reconvened within a month on 7 days' notice. If quorum is still not met, the meeting is cancelled, and the same matter cannot return to an SGM for three months. Video-conferencing members count towards quorum and majority, but at least 51% of total members must be physically present.

25. What majority is required to pass a redevelopment resolution?

A redevelopment resolution needs the support of 51% of the society's total membership, not just 51% of those merely present. This is a stricter test than an ordinary resolution, which only needs 51% of members actually present at the meeting.

26. Give an example of how the physical-presence rule works with numbers.

For a society of 100 total members, the quorum is 67 members (two-thirds), and the resolution needs 51 members' support. Of those 51 or more supporting members, at least 51 must be physically present in the room — video conferencing can only help reach numbers above this physical minimum, not replace it.

27. Who prepares the Project Report, and within what time?

The appointed PMC or architect must prepare the Project Report within two months of their appointment. This report sets out the technical and financial basis on which the redevelopment proposal is built.

28. How long does the Managing Committee have to review the Project Report?

The Managing Committee must review the Project Report within 30 days of receiving it. This ensures the report is examined promptly rather than being left pending indefinitely before the next SGM is called.

29. Where must the tender notice be published?

The tender notice must be published in local newspapers, in both Marathi and English, so that it reaches a wide pool of genuine, qualified bidders. Relying only on word-of-mouth or a notice-board posting is not sufficient under this GR.

30. What happens if the number of tenders is still short after the first extension?

If three tenders are still not received after the first 15-day extension, the society must extend the tender period by a further 7 days. Only after both extensions have been genuinely exhausted can the society proceed with whatever valid tenders it has actually received.

31. Within how many days must the Registrar appoint an Authorised Officer?

The Registrar must decide on the appointment within 14 days of receiving the society's complete proposal. After the officer is appointed, the Secretary must convene the developer-selection SGM within one month.

32. How is the vote conducted at the developer-selection meeting?

The vote is normally by show of hands. If at least one-fifth of the society's total members demand it in writing, the vote must instead be by secret ballot, arranged by the Authorised Officer, with the cost borne by the society.

33. What happens within 14 days after the developer-selection meeting?

A detailed report of the meeting, including the video recording and the resolution passed, must be filed with the Registrar within 14 days. This strict reporting timeline creates an official, timely record that the correct procedure was followed.

34. Within how long must the Development Agreement be signed after developer selection?

The Development Agreement with the selected developer must be executed within three months of the SGM at which the developer was chosen. This stops an unreasonable gap between selecting a developer and actually formalising the legal terms with them.

35. What must the Development Agreement say about bank guarantee and alternate accommodation?

The General Body must approve the percentage and form of the developer's bank guarantee. The agreement must also provide alternate accommodation during construction: nearby where possible, or monthly rent and deposit acceptable to members, or transit accommodation.

36. What does the GR say about carpet area disclosure?

The carpet area of the flats to be given to members must be disclosed in accordance with RERA requirements. This ensures members know the exact, legally defined area they will receive, rather than relying on informal or approximate figures.

37. Can development rights be transferred to another party by the developer?

No. The development rights granted to the selected developer are non-transferable, meaning the developer cannot simply hand over or sell the project to a different party without the society's fresh approval through the proper process.

38. How is a dispute between the society and developer to be resolved?

The Development Agreement must include a clause that any dispute will be taken to the competent court or authority under the prevailing law. The GR does not specifically mention arbitration.

39. How are new flats allotted among members?

New flats are allotted among members by floor-order or by a draw of lots, and this allotment process must be video recorded. This transparent method ensures no member or group of members gets an unfair advantage in choosing their new flat.

40. What procedure applies when several societies redevelop together (cluster/federation)?

When societies redevelop together through a registered federation (Sahakari Gruhnirman Sangh), the federation itself needs two-thirds quorum and 51% approval at its own level. In addition, each individual affiliated society separately needs its own two-thirds quorum SGM and 51% approval of its own total members — or, as an alternative, an aggregate 60% approval across all affiliated societies' members combined.

Routine & Administrative Matters

41. How are fractions handled when calculating quorum or majority numbers?

Wherever a calculation of quorum or majority results in a fraction, that fraction is always rounded up to the next whole number. For example, a calculation resulting in 50.2 members would be rounded up to 51 members, not down to 50.

42. Can members inspect redevelopment documents?

Yes. Members have the right to inspect redevelopment-related documents, such as the Project Report, tender documents and the Development Agreement, free of cost. This supports the transparency that is one of the main purposes of this GR.

43. Is there a fee for certified copies of documents?

A member can obtain certified copies of these documents, but a prescribed fee applies for certified copies, unlike free inspection of the original documents. This fee only covers the cost of providing an official certified copy.

44. Must sanctioned building plans be shown to members?

Yes. Once the building plans are sanctioned by the municipal or planning authority, they must be presented to the General Body of the society. This keeps members informed of the exact design and scale of the project they have approved.

45. When must new flat owners be made members of the society?

When a new flat-holder takes possession and applies for membership, the society's committee must decide within three months and issue membership and a share certificate.

46. Does this GR cover old agreements signed before 30 September 2026?

The GR does not expressly say how it applies to agreements signed before 30 September 2026. Take advice on your Society's own position before acting.

47. Who is responsible for filing reports with the Registrar?

The Secretary of the society is generally responsible for retaining meeting records and ensuring reports, including the video recording and resolution, are filed with the Registrar within the prescribed timelines. The Managing Committee as a whole remains accountable for this being done correctly.

48. Does this GR override the society's bye-laws?

The GR does not expressly address bye-laws. Where a bye-law appears to conflict with the GR's mandatory procedure, take advice before relying on that bye-law.

49. Where can a society get a copy of this GR?

The GR is published on the Government of Maharashtra's official website, www.maharashtra.gov.in, and carries an official code and digital signature for verification. A society's PMC or legal consultant can help locate and verify the exact published copy.

50. What should a society do first after reading this GR?

A society should first place this GR before its Managing Committee, and if redevelopment is already underway, compare its current stage of work against this GR's requirements with the help of its PMC or legal consultant. Acting early avoids having to redo steps that were not aligned with this GR's mandatory procedure.

*******************************

Disclaimer : for Information and Academic Purpose Only.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.

गृहनिर्माण संस्थेच्या पुनर्विकासाची ३० टप्प्यांची प्रक्रिया - (30-Step Process of Redevelopment of a Housing Society).

  गृहनिर्माण संस्थेच्या पुनर्विकासाची ३० टप्प्यांची प्रक्रिया 30-Step Process of Redevelopment of a Housing Society 1. पुनर्विकास समजून घेणे...